AQW 30324/22-27


Ms Claire Sugden
Independent
East Londonderry


Tabled Date: 04/09/2025
Answered On Date: 22/09/2025
Priority Written: No


Question:
To ask the Minister for Infrastructure to detail the total length of time that traffic management measures have been in place in Ballykelly, as a result of roadworks, in the last three years.


Answer:
Over the past three years there have been approximately 230 days of restricted hours lane closures on the A2 Clooney Road in Ballykelly and Walworth.
In addition, there have been 10 days of full night-time carriageway closure with a diversion route for carriageway resurfacing.
The majority of the works are attributable to my department and involve investment of over £3m in the area.