AQW 30980/22-27


Miss Nuala McAllister
Alliance Party
North Belfast


Tabled Date: 11/09/2025
Answered On Date: 30/09/2025
Priority Written: No


Question:
To ask the Minister for Infrastructure to detail any road repairs carried out on (i) Farmley Park; and (ii) Farmley Gardens, Newtownabbey, in the last 24 months.


Answer:
Defects within Farmley Park and Gardens, which have resulted in road repairs in the last 24 months, are detailed below:
Farmley Park
Farmley Gardens
9 carriageway defects (potholes)
8 repaired / 1 outstanding
9 carriageway defects (potholes)
7 repaired / 2 outstanding
2 footway defects (potholes)
complete
2 footway defects (potholes)
1 repaired / 1 outstanding
3 road marking defects
2 repaired / 1 outstanding
1 road marking defects
1 outstanding