AQW 32847/22-27


Mr Eóin Tennyson
Alliance Party
Upper Bann


Tabled Date: 06/10/2025
Answered On Date: 14/10/2025
Priority Written: No


Question:
To ask the Minister for Infrastructure, pursuant to AQW 24902/22-27, for an update on her Department’s assessment of the business case, submitted by Translink, for the Lurgan signalling improvement project.


Answer:
This Outline Business Case (OBC) is currently being assessed by my officials and once complete, and if appropriate, they will seek approval from colleagues in the Department of Finance. Subject to securing approval of the full business case, the availability of funding, along with other various required statutory approvals, the project could commence in September 2028 and take one year to complete.