AQW 32921/22-27 Mr David Honeyford Alliance Party Lagan Valley
Tabled Date: 07/10/2025 Answered On Date: 30/10/2025 Priority Written: No
Question: To ask the Minister of Health for a breakdown of the £2.5 billion spent on IT, in the three financial years to 2024-25.
Answer:
The Northern Ireland Audit Office published a report on “Major IT projects in Northern Ireland” on 4th July 2025. Appendix 2 of the report summarises Major IT programmes and projects in excess of £25million (whole life cost) ongoing from 1 April 2022 to 31 March 2025. The section relating to Department of Health shows the following: Major IT Project | Original expiration date of legacy contract | OBC Total estimated costs £million | FBC Total estimated costs £million | Actual / latest total estimated costs £million | Increase/ (decrease) estimated costs from OBC £million | Northern Ireland Picture Archiving and Communication System | Sep-18 | 136.5 | 130.4 | 130.4 | (6.1) | Northern Ireland Digital Identity Service | Sep-21 | 38.2 | 38.1 | 39.3 | 1.1 | Encompass See Case Study 1 | Multiple contracts | 982.5 | 1,950.0 | 1,930.0 | 947.5 | Equip Programme | Oct-21 | 145.1 | 218.2 | 218.2 | 73.1 | Core Laboratory Information Management System | Replaces 7 existing systems | 44.0 | 44.0 | 57.8 | 13.8 | Regional Blood Production and Tracking Solution | Jun-23 | 36.0 | 38.9 | 38.9 | 2.9 | ePharmacy Project 1 - GoPharmacy NI Note: OBC not yet submitted, figures are estimated. | | 19.4 | 19.4 | 19.4 | - | ePharmacy Project 2 - Electronic Transfer of Prescriptions Note: OBC not yet submitted, figures are estimated. | | 38.4 | 38.4 | 38.4 | - | Total | | 1,440.1 | 2,477.4 | 2,472.4 | 1,032.3 |
Major IT Project | Implementation completion date | Stage project currently at | Latest project highlight report RAG status | Northern Ireland Picture Archiving and Communication System | Dec-25 | Implementation | Green | Northern Ireland Digital Identity Service | Mar-26 | Implementation | Green | Encompass See Case Study 1 | Sep-27 | Implementation | Green | Equip Programme | Sep-26 | Implementation | Red | Core Laboratory Information Management System | Mar-26 | Implementation | Amber | Regional Blood Production and Tracking Solution | Sep-27 | Implementation | Green | ePharmacy Project 1 - GoPharmacy NI Note: OBC not yet submitted, figures are estimated. | Subject to funding | Initiation | Amber | ePharmacy Project 2 - Electronic Transfer of Prescriptions Note: OBC not yet submitted, figures are estimated. | Subject to funding | Initiation | Amber |
Major IT programmes and projects (in excess of £25million whole life cost) ongoing from 1 April 2022 to 31 March 2025 in Department of Health The 8 major Department of Health digital initiatives listed in the report have full life commitments of £2.477 billion. It should be noted that expenditure on the ePharmacy initiative is indicative as this has not yet been funded or approved.
|