AQW 33049/22-27


Mr Nick Mathison
Alliance Party
Strangford


Tabled Date: 08/10/2025
Answered On Date: 14/10/2025
Priority Written: Yes


Question:
To ask the Minister of Education to detail when Clarawood School, Belfast, will be granted full access to the Willow Building, located on their site, for classroom provision.


Answer:
The Education Authority (EA) has advised it is currently anticipated that Willow will leave the existing building at the Clarawood school site, allowing Clarawood to move into the ‘Willow Building’, following the successful installation of temporary rental accommodation at another local EA site. This is currently estimated with a target completion of November 2025.