AQW 33063/22-27


Mrs Diane Dodds
Democratic Unionist Party
Upper Bann


Tabled Date: 08/10/2025
Answered On Date: 10/12/2025
Priority Written: No


Question:
To ask the Minister of Health, since the commencement of the construction of the new Maternity Hospital in Belfast, to detail (i) each extension of time that was requested; (ii) the reason for the extension request; (iii) who made the request; (iv) how much time it added; and (v) the estimated cost of each extension.


Answer:
Extensions of Time (EoTs) are dealt with and assessed under the conditions of the construction contract under which there are aspects of commercial confidentiality. This response provides an overview and totals in relation to your request.
Since the commencement of the construction of the New Maternity Hospital in Belfast, there have been sixteen EoT requests made under the contract.
The reasons for the EoT requests included Change Control Orders (CCOs) and Project Manager’s Instructions (PMIs) regarding;
Fire safety matters;
Compliance with Building Control requests;
Works on adjacent parts of the Royal Victoria Hospital site which had an impact on the Maternity Hospital site (e.g., underground ducts, flues);
Covid-19 related site closure and delays;
Amendments to internal layouts, ventilation and bedhead arrangements including those impacted by Medical Gas installations, internal ducting and cabling;
Time taken to approve systems such as Nurse Call and Emergency Lighting systems and to confirm sitewide existing medical gas capacity;
Delay in receipt of comments from the Approved Person (AP) in relation to medical gases;
Delays to medical gas inspection and commissioning;
Water-on delay; and
Domestic water systems splashing remediation.
Each EoT request was made by the contractor.
The total time requested by the contractor under EoTs 1-16 inclusive amounted to 257.86 weeks. The total time awarded to the contractor amounted to 183.7 weeks.
The estimated cost associated with the total of EoTs awarded is c. £17.4m.