AQW 35393/22-27


Mrs Ciara Ferguson
Sinn Féin
Foyle


Tabled Date: 13/11/2025
Answered On Date: 28/11/2025
Priority Written: No


Question:
To ask the Minister of Health for an update on work undertaken by his Department in the last six months to progress the Cityside Health and Care Centre at Fort George, Derry.


Answer:
The Western Health and Social Care Trust has completed RIBA Stage 3 for the new Cityside Health and Care Centre Hub at Fort George. A full planning application was submitted at the end of July 2025 to Derry City and Strabane District Council.
Funding to complete the remaining design and deliver the project is subject to finalisation of the Department’s Strategic Capital Development plan, the outcome of which is anticipated early 2026.
My ability to commit funding for this project will depend on the Department’s capital allocation from the budget process and the identification of sufficient recurrent funding to meet any additional resource costs associated with the facility.