AQW 37128/22-27


Mr Daniel McCrossan
Social Democratic and Labour Party
West Tyrone


Tabled Date: 09/12/2025
Answered On Date: 22/12/2025
Priority Written: Yes


Question:
To ask the Minister of Education for an update on the Strule Shared Education Campus project, in particular any reason for the reduction in need for capital spend of £18.4million this financial year, as identified in the December Monitoring Round.


Answer:
Significant progress continues on the Strule Shared Education Campus (SSEC) Main Works Construction with 25% of the Main Works now complete. All works remain within the Full Business Case approval and programme limits. Planned construction completion is November 2027 with full campus opening by September 2028.
The £18.4m reduced requirement submitted as part of the December Monitoring Round takes account of a revised anticipated expenditure profile to the end of March 2026 which reflects unexpected programme delays (largely relating to challenging ground conditions encountered at the Shared Education Centre). It also takes account of an assessment of the current position in terms of Contractor procurement activities and the estimated cost of implemented and expected change.