AQW 37322/22-27 Mr Justin McNulty Social Democratic and Labour Party Newry and Armagh
Tabled Date: 11/12/2025 Answered On Date: 26/01/2026 Priority Written: No
Question: To ask the Minister for Infrastructure, pursuant to AQW 32527/22-27, (i) for an update on when the tender documents for the A1 Junctions Phase 2 Scheme will be issued; and (ii) to detail the expected timeline for project completion.
Answer:
The A1 Junctions Phase 2 Project will deliver enhanced safety measures along the A1 route, costing in the region of £120 - £130m and will include the closing up of all gaps in the central median and the provision of a number of new grade separated junctions. The scheme was confirmed by my predecessor John O’Dowd as a single package of works on 2 July 2024 and a restricted list was notified to tenderers on 9 May 2025. Since the judgment on the A5 Western Transport Corridor project and the Department’s appeal, I am taking time to carefully consider the potential impact on other projects as they move through the next stages of their delivery, this includes the A1 Junctions Phase 2 Project. While we await the ruling from the Court Appeal, my officials continue to work on the next steps in relation to the project and I remain committed to the delivery of this vitally important safety scheme.
|