Question:
To ask the Minister for Infrastructure, in light of the increased amount of flooding expected on already saturated land, for an update of the Living With Water Programme.


Answer:
The formal programme structures for the 12-year Living With Water in Belfast Plan were stood down in December 2024, following an affordability review, prompted by a £700m increase in the estimated cost of delivering the NI Water elements of the Plan. The review reaffirmed the need for the Belfast Plan, but concluded that the original 12-year delivery timeframe is no longer achievable.
Projects within the Belfast Plan will still proceed, led by my Department and NI Water, but at a scale and pace aligned with available budgets, rather than through a formal programme structure.
NI Water has therefore deferred delivery of major upgrades needed to wastewater infrastructure around Belfast Lough including Sydenham Pumping Station and wastewater treatment works at Belfast, Whitehouse and Kinnegar. NI Water will instead prioritise additional maintenance to ensure these assets remain operational until funding for significant upgrades becomes available.
While the Plan was always expected to require additional investment, as referenced in the New Decade New Approach agreement, this has not been provided by the British Government.
I remain committed to the objectives of the Belfast Plan, to help protect against flooding, enhance the environment and grow the economy, and I will continue to advocate for the additional funding needed to expedite the delivery of projects within the Plan.