AQW 40138/22-27


Mr Daniel McCrossan
Social Democratic and Labour Party
West Tyrone


Tabled Date: 09/02/2026
Answered On Date: 13/02/2026
Priority Written: No


Question:
To ask the Minister of Education, pursuant to AQW 37128/22-27, for an update on the Strule Shared Education Campus project, in particular the £6.4million reduction in capital spend announced.


Answer:
Significant progress continues on the Strule Shared Education Campus (SSEC) Main Works Construction with just under 27% of the Main Works now complete. All works remain within the Full Business Case approval and programme limits.
The construction is due to be completed by November 2027 with full campus opening by September 2028.
The reduced requirement of £6.4m reflects some minor impacts on the contract programme due to the exceptional weather conditions which has meant that the projected expenditure profile would not be realised for this financial year.