AQW 40768/22-27 Ms Claire Sugden Independent East Londonderry
Tabled Date: 17/02/2026 Answered On Date: 04/03/2026 Priority Written: No
Question: To ask the Minister for Infrastructure to detail the £3.8 million estimated cost of the proposed park and ride facility at Bellarena railway halt, including a breakdown of costs for (i) design; (ii) land acquisition; (iii) construction; and (iv) associated works.
Answer:
The table below provides a breakdown of estimated costs to deliver the new Park and Ride facility at Bellarena Rail Halt. Item | Cost | Construction | £2,794,701 | Project management, design and statutory fees | £259,419 | Optimum Basis and sunk costs | £547,836 | Inflation | £221,924 | Total | £3,823,880 |
|