AQW 41662/22-27


Mrs Michelle Guy
Alliance Party
Lagan Valley


Tabled Date: 02/03/2026
Answered On Date: 13/03/2026
Priority Written: No


Question:
To ask the Minister for Infrastructure to detail any actions her Department is taking to address the frequent flooding on Warren Park, Lisburn.


Answer:
My officials visited Warren Park on 27 February 2026 to assess the condition of the road gullies in the area when three of the four gullies were fully cleaned. An issue was identified with the outlet pipe in the remaining gully, and arrangements are in place to have this addressed by the end of March 2026.