AQW 43197/22-27


Mr Brian Kingston
Democratic Unionist Party
North Belfast


Tabled Date: 25/03/2026
Answered On Date: 13/05/2026
Priority Written: No


Question:
To ask the Minister of Health whether he has a timescale for when the new Belfast Maternity Hospital will be ready for public use.


Answer:
The Belfast Health and Social Care Trust have advised that the consultant design team for the remediation works to the water systems within the new Belfast Maternity Hospital has been appointed. The team commenced work on the design of a new domestic water system within the neonatal unit in October 2025.
 
In addition to the provision of a new domestic water system within the neonatal intensive care unit, the proposed remediation works also involve localised remediation to the water systems throughout the remainder of the building.
 
Belfast Trust received a draft “Stage 1” design report from the consultant design team in April 2026. This report is currently being reviewed by the Trust and DoH Health Estates, and a number of areas for clarification have been requested, including updated cost estimates and the programme showing the phasing of the remediation works. A summary paper will be shared with the Health Committee once the report has been accepted by Trust Board.
The initial phase of the remediation work, including the isolation of the existing neo-natal water system and strip out work will now commence.
The full remediation works are anticipated to take approximately 24 months to complete.
I have asked the Belfast Health and Social Care Trust to look at the feasibility of a phased opening of the new Maternity Hospital.