AQW 48997/22-27


Mrs Diane Dodds
Democratic Unionist Party
Upper Bann


Tabled Date: 18/06/2026
Answered On Date: 27/07/2026
Priority Written: No


Question:
To ask the Minister of Health for an update on (i) any cost of payments made by the by the Belfast Health and Social Care Trust to the contractor for the new Children’s Hospital for adjustments or variations to the works (ii) details of the work required (iii) the total of any outstanding payments for adjustments or variations


Answer:
The Belfast Health and Social Care Trust previously advised that they had conducted a Public Interest Test in relation to this matter. Following this assessment, they concluded that they were unable to release the requested information, as it is considered commercially sensitive.
I can however advise that the total of payments made by the Belfast Health and Social Care Trust to the contractor on the new Children’s Hospital for adjustments or variations to the works up to 2 July 2026 is £3,033,884. The adjustments and variations included, inter alia, changes in relation to piling, retaining walls, quantities remeasurement, human resources, asbestos clearance, temporary services, NIE supply, statutory regulations, services and drainage amendments.
There are no outstanding payments for adjustments or variations.