AQW 51601/22-27 Mr Eóin Tennyson Alliance Party Upper Bann
Tabled Date: 10/09/2026 Answered On Date: 21/09/2026 Priority Written: No
Question: To ask the Minister of Education for an update on any progress made for the extension to St Mary's Primary School, Banbridge, following its recent planning approval.
Answer:
Following the successful receipt of planning approval, the Integrated Consultancy Team has been instructed to provide updated costs, including the implementation of appropriate traffic management measures, for consideration prior to proceeding with the preparation and issue of tender documentation for the construction works. Subject to approval, it is anticipated that the tender for the construction works will be issued in the New Year.
|