AQW 53543/22-27


Ms Paula Bradshaw
Alliance Party
South Belfast


Tabled Date: 01/10/2026
Answered On Date: 15/10/2026
Priority Written: No


Question:
To ask the Minister for Infrastructure for an update on the delivery of Phase 2 of the Belfast Rapid Transit project.


Answer:
The outline business case for Belfast Rapid Transit Phase 2 (BRT2) was approved in December 2025 with an estimated delivery cost of approximately £124.5m. Currently, £35m has been allocated from the Belfast Region City Deal and I have committed an additional £13m from my Department to progress a phased delivery of the project. The estimated cost of the project will continue to be reviewed at appropriate stages throughout development and delivery.
Since April 2026, consultants have been progressing work on design phase of the scheme. Geotechnical investigation works are being carried out at several locations to inform the design development, and engagement with key stakeholders continues.
A draft delivery programme has been developed and indicates that construction commence in 2027, with the Bankmore Link section of the project progressing as one of the early phases. However, the programme is dependent on a range of factors including obtaining the necessary planning and environmental approvals from the Council, operational requirements and stakeholder engagement.