AQW 3112/11 Mr Patsy McGlone Social Democratic and Labour Party Mid Ulster
Tabled Date: 15/12/2010 Answered On Date: 21/12/2010 Priority Written: No
Question: To ask the Minister of Justice, in light of the budget announcement of 15 December 2010, what financial commitment his Department has made to the Desertcreat college development; and to outline the expected timescale for the project.
Answer:
Following the publication of the Draft Budget, details of my Department’s budget allocations will be published as soon as possible. This will include the financial commitment for the Desertcreat college development. Subject to DFP approval of the business case, the timeline for construction is as follows: Design completion and procurement prequalification - February 2011 to November 2011. Detailed procurement process leading to appointment of contractor – November 2011 to April 2012 Construction of college – May 2012 to June 2014.
|